Project Description
Project Overview
This was a true design build project that challenged the Development and Construction team to work in a fast paced fluid environment.
Site grading started on August 10th and by November 20th the first 600,000 sft. Building and arterial road was completed and paved. Engineering and infield construction crews worked seamlessly to drive the project schedule and site adjustments. Early in the preconstruction phases poor soil layers were identified that would have lead to substantial cost over runs and project delays if not identified early on and re engineered. This is an example of proactive site management that leads to success for everyone involved.
Project Details
DATE
July 2018
LOCATION
Somers, WI
PARTNERS
First Industrial
PROJECT TYPE
Commercial
SERVICES PROVIDED
Value engineering, mass grading 250 acres, soil stabilization, sanitary, water, storm sewer, building excavation for 2 each 600,00 sft. buildings, basecourse, concrete curb, paving, landscaping, irrigation, and ongoing site maintenance.